Air Quality Permit Modification Request
This request is to modify the University's Approval Order and Operating Permit.Construction of a source may begin upon receipt of the modified Approval Order by the Environmental Affairs Manager.
Operation of the equipment may begin upon receipt of the modified Operating Permit by the Environmental Affairs Manager.
Project Managers must allow at least 3 months lead time for the modified Approval Order (aka construction permit).
Allow at least 6 months for the modified Operating Permit.
The Division of Air Quality (DAQ) estimates permit fees based on project information. Filing and base review fee will be due prior to submittal of the application to the DAQ.
| Permit fees are as follows: | hours | base fee | additional hours - hourly rate |
| filing | not applicable | $500 | not applicable |
| review - minor modification | 20 | $1,400 | $70 |
| review - major modification | 450 | $31,500 | $70 |