Air Quality Permit Modification Request

This request is to modify the University's Approval Order and Operating Permit.
Construction of a source may begin upon receipt of the modified Approval Order by the Environmental Affairs Manager.
Operation of the equipment may begin upon receipt of the modified Operating Permit by the Environmental Affairs Manager.
Project Managers must allow at least 3 months lead time for the modified Approval Order (aka construction permit).
Allow at least 6 months for the modified Operating Permit.

The Division of Air Quality (DAQ) estimates permit fees based on project information. Filing and base review fee will be due prior to submittal of the application to the DAQ.

Permit fees are as follows: hours base fee additional hours - hourly rate
filing not applicable $500 not applicable
review - minor modification 20 $1,400 $70
review - major modification 450 $31,500 $70

Requested by:

E-mail:

Phone:

Fax:

Project or work order number:

Building number:

Building name :

Equipment type (natural gas-fired generator, diesel-fired generator, dual-fuel boiler, natural gas boiler, etc.):
Equipment size (kw, hp, heat input in BTU/hr):
Emission rates (manufacturer gaurantees) include unit (e.g. grams/hp-hr) NOx
  SOx
  PM10
  CO
  VOCs
Projected equipment use schedule (e.g.; emergency backup; 3 hours per day 5 days per week; etc.)
Project timeline
Construction commencement:
Project completion: